In a building construction project, the on-time completion of the building requires the successive completion of a series of activities. Define E = excavation completed on time; and P[E] = 0.8 F = foundation completed on time; and P[F] = 0.7 S = superstructure completed on time; and P[S] = 0.9 Assume statistical independence among these events.

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 20.06.2019 18:04, babas97
Asap (explain how you got it as well for brainliest)i tried 1: 2 and 2: 3 and they were wrong. picture of figure: in the figure below, the segment is parallel to one side of the triangle. the ratio of 12 to y is1: 21: 31: 42: 3
Answers: 1
image
Mathematics, 21.06.2019 14:00, miriamnelson7545
△cde maps to △stu with the transformations (x, y) arrowright (x − 2, y − 2) arrowright (3x, 3y) arrowright (x, −y). if cd = a + 1, de = 2a − 1, st = 2b + 3 and tu = b + 6, find the values of a and b. the value of a is and the value of b is .
Answers: 1
image
Mathematics, 21.06.2019 19:30, dessyrob05
Factor the expression using gcf 9b+45
Answers: 2
image
Mathematics, 21.06.2019 22:30, hannahkharel2
What is the least common multiple for 6 and 8? what is the least common multiple for 4 and 12 ? what is the least common multiple for 11 and 12? what is the least common multiple for 3 and 6?
Answers: 1
You know the right answer?
In a building construction project, the on-time completion of the building requires the successive c...