Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $200,000 10,000 MHs
Machine setups Number of setups $100,000 200 setups
Production design Number of products $84,000 2 products
General factory Direct labor-hours $300,000 12,000 DLHs
Activity Measure Product Y Product Z
Machining 8,000 2,000
Number of setups 40 160
Number of products 1 1
Direct labor-hours 9,000 3,000
1. What is the company’s plantwide overhead rate?
2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z?
3. What is the activity rate for the Machining activity cost pool?
4. What is the activity rate for the Machine Setups activity cost pool?
5. What is the activity rate for the Product Design activity cost pool?
6. What is the activity rate for the General Factory activity cost pool?
7. Which of the four activities is a batch-level activity?
8. Which of the four activities is a product-level activity?
9. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y?
10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z?
11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z?
12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z?
13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)
14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z?
15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z?

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 10:40, jonnaevans4856
You were able to purchase two tickets to an upcoming concert for $100 apiece when the concert was first announced three months ago. recently, you saw that stubhub was listing similar seats for $225 apiece. what does it cost you to attend the concert?
Answers: 1
image
Business, 22.06.2019 19:00, sharri44
Read the scenario. alfonso is 19 years old and has a high school diploma. recently, he was promoted to assistant manager at the fast-food restaurant where he has worked since the age of sixteen. his dream is to become the restaurant’s manager. what is his best option for achieving his dream? he should find another job and work his way up to a higher position. he should hope that his manager transfers to another location and that he is his replacement. he should attend classes at the local college to receive training in management. he should work hard, work longer hours, and remain assistant manager.
Answers: 2
image
Business, 23.06.2019 02:30, d1Dej
Markets and competition in a perfectly competitive market, all producers sell identical goods or services. additionally, there are many buyers and sellers. because of these two characteristics, both buyers and sellers in perfectly competitive markets are pricetakers . true or false: the market for lettuce does exhibit the two primary characteristics that define perfectly competitive markets. true false
Answers: 2
image
Business, 23.06.2019 03:10, thedeathlord123
He cheyenne hotel in big sky, montana, has accumulated records of the total electrical costs of the hotel and the number of occupancy-days over the last year. an occupancy-day represents a room rented out for one day. the hotel's business is highly seasonal, with peaks occurring during the ski season and in the summer. month occupancy- days electrical costs january 1,736 $ 4,127 february 1,904 $ 4,207 march 2,356 $ 5,083 april 960 $ 2,857 may 360 $ 1,871 june 744 $ 2,696 july 2,108 $ 4,670 august 2,406 $ 5,148 september 840 $ 2,691 october 124 $ 1,588 november 720 $ 2,454 december 1,364 $ 3,529 required: 1. using the high-low method, estimate the fixed cost of electricity per month and the variable cost of electricity per occupancy-day. (do not round your intermediate calculations. round your variable cost answer to 2 decimal places and fixed cost element answer to nearest whole dollar amount) 2. what other factors other than occupancy-days are likely to affect the variation in electrical costs from month to month? (you may select more than one answer. single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) seasonal factors like winter or summer. systematic factors like guests, switching off fans and lights. number of days present in a month. fixed salary paid to hotel receptionist. income taxes paid on hotel income.
Answers: 2
You know the right answer?
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z....

Questions in other subjects:

Konu
Chemistry, 11.03.2020 03:32
Konu
History, 11.03.2020 03:32