C. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21. (Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.)

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 20:30, isidrocastanonox22wl
Monetary policy in the united states is carried out primarily by which of the following agencies? a. the department of the treasury b. the small business association c. the federal reserve bank d. the u. s. mint 2b2t
Answers: 1
image
Business, 21.06.2019 20:30, jess7kids
Anewspaper boy is trying to perfect his business in order to maximize the money he can save for a new car. daily paper sales are normally distributed, with a mean of 100 and standard deviation of 10. he sells papers for $0.50 and pays $0.30 for them. unsold papers are trashed with no salvage value. how many papers should he order each day and what % of the time will he experience a stockout? are there any drawbacks to the order size proposed and how could the boy address such issues?
Answers: 3
image
Business, 22.06.2019 13:40, ilovecatsomuchlolol
A. j. was a newly hired attorney for idle time gaming, inc. even though he reported directly to the president of the company, a. j. noticed that the president always had time to converse with the director of sales, calling on him to get a pulse on legal/regulatory issues that, as the company attorney, a. j. could have probably handled. a. j. also noted that the hr manager’s administrative assistant was the go-to person for a number of things that would make life easier at work. a. j. was recognizing the culture at idle time gaming.
Answers: 3
image
Business, 22.06.2019 18:10, salvadorperez26
Find the zeros of the polynomial 5 x square + 12 x + 7 by factorization method and verify the relation between zeros and coefficient of the polynomials
Answers: 1
You know the right answer?
C. Suppose it is now the end of the seventh day and that activities A and B have been completed whil...

Questions in other subjects:

Konu
Mathematics, 17.12.2019 03:31
Konu
Mathematics, 17.12.2019 03:31