Meghan's team is comprised of 10 people who work 40 hours per week. The team is tasked with completing a project that requires 700 man-hours

in one week. To complete the project, Meghan plans to add n members to

the team and have each team member work an extra 3n hours that week.

What is the minimum number of extra team members she needs?

ansver
Answers: 2

Other questions on the subject: SAT

image
SAT, 22.06.2019 10:20, stefan19367
One common system for computing a grade point average (gpa) assigns 4 points to an a, 3 points to a c, 1 point to a d, and 0 points to an f. what is the gpa of a student who gets an a in a 3 credit course, a b in each of two 2 credit courses, and a d in a 2 credit course?
Answers: 1
image
SAT, 26.06.2019 00:00, Jonah58
17 a tourist was planning a trip by car for travelling at some constant speed for 2.5 hours. however, he found that if he increases the speed by 20 km/h he can cover the same distance in 30 minutes less time than it was planned. what was the planned speed of the tourist, in km/h?
Answers: 1
image
SAT, 28.06.2019 16:00, cocoj3205
Select all that apply. select six of the aspects summarized in this section in which god's goodness is imparted to his people. mercy truth righteousness love compassion grace holiness strength majesty perfection
Answers: 1
image
SAT, 30.06.2019 00:00, dianepowers1
Wiosiy tost type the correct answer in the box. spell all words correctly. which economy enables demand for a product or service to drive all the business decisions? business decisions are driven by demand in a (an) economy reset next
Answers: 1
You know the right answer?
Meghan's team is comprised of 10 people who work 40 hours per week. The team is tasked with complet...

Questions in other subjects:

Konu
Mathematics, 06.06.2020 14:58