SAT, 18.03.2021 01:50 Mariela2699
Meghan's team is comprised of 10 people who work 40 hours per week.
The team is tasked with completing a project that requires 700 man-hours
in one week. To complete the project, Meghan plans to add n members to
the team and have each team member work an extra 3n hours that week.
What is the minimum number of extra team members she needs?
Answers: 2
SAT, 22.06.2019 10:20, stefan19367
One common system for computing a grade point average (gpa) assigns 4 points to an a, 3 points to a c, 1 point to a d, and 0 points to an f. what is the gpa of a student who gets an a in a 3 credit course, a b in each of two 2 credit courses, and a d in a 2 credit course?
Answers: 1
SAT, 26.06.2019 00:00, Jonah58
17 a tourist was planning a trip by car for travelling at some constant speed for 2.5 hours. however, he found that if he increases the speed by 20 km/h he can cover the same distance in 30 minutes less time than it was planned. what was the planned speed of the tourist, in km/h?
Answers: 1
SAT, 30.06.2019 00:00, dianepowers1
Wiosiy tost type the correct answer in the box. spell all words correctly. which economy enables demand for a product or service to drive all the business decisions? business decisions are driven by demand in a (an) economy reset next
Answers: 1
Meghan's team is comprised of 10 people who work 40 hours per week.
The team is tasked with complet...
Mathematics, 06.06.2020 14:58
Mathematics, 06.06.2020 14:58
English, 06.06.2020 14:58