The number of days needed to remodel a house varies inversely as the number of people working on the job. it takes 18 weeks for 4 people to complete the project. if the job has to be finished in 8 weeks, how many people are needed?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 17:50, AdanNava699
Find the cosine function that is represented in the graph.
Answers: 1
image
Mathematics, 21.06.2019 18:00, summer996
If you had $1,900,000, how many days would it take you to spend all if you spent $1 a second. (there are 86,400 seconds in a day)
Answers: 1
image
Mathematics, 21.06.2019 23:00, laya35
Which of the following graphs could represent a cubic function?
Answers: 1
image
Mathematics, 21.06.2019 23:30, joelpimentel
Which choice has the correct steps in graphing the solution set to the following inequality? -45_> 20x-5y
Answers: 1
You know the right answer?
The number of days needed to remodel a house varies inversely as the number of people working on the...