You work as a coordinator for data entry projects. on one project, the status report shows that 15% of the work was completed in 6 days. if the work progresses at the same rate, how many more days will be required to complete the remainder of the project?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:00, nicolemaefahey
How do i start to solve? would appreciate a walk-thru! a bird sitting 16ft above the ground in an apple tree dislodges an apple. after how many seconds does the apple land on the ground? (assuming that no branches will interfere with it's fall)
Answers: 1
image
Mathematics, 21.06.2019 21:00, Neko1kat
Solve this problem! extra ! 3025/5.5 = a/90.75
Answers: 1
image
Mathematics, 21.06.2019 21:50, indexes06
Which of the following equations is equivalent to x/3-6/x=1
Answers: 3
image
Mathematics, 21.06.2019 22:00, PROMASTER
Asquare and an equilateral triangle have the same perimeter. each side the triangle is 4 inches longer than each side of the square. what is the perimeter of the square
Answers: 1
You know the right answer?
You work as a coordinator for data entry projects. on one project, the status report shows that 15%...

Questions in other subjects:

Konu
Law, 04.03.2021 22:20
Konu
Mathematics, 04.03.2021 22:20
Konu
Mathematics, 04.03.2021 22:20
Konu
Social Studies, 04.03.2021 22:20