Your boss estimates it take 42 person - hours to rearrange the floor plan for the produce department at a local grocery store. your boss would like to complete the job in 9 hours. how many workers are necessary to complete the job in this amount of time?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:20, kuehlthau03
Which is the equation of an ellipse with directrices at x = ±4 and foci at (2, 0) and (−2, 0)?
Answers: 3
image
Mathematics, 21.06.2019 17:00, Uc34758
Which simplifys to a+ b? a-(1-b)+1 -(1-a)-b+1 (a--1) -1)+1
Answers: 1
image
Mathematics, 21.06.2019 17:00, zivicion
5(-9w) put expression in distributive property
Answers: 1
image
Mathematics, 21.06.2019 18:30, Angelanova69134
Someone answer this asap rn for ! a discount store’s prices are 25% lower than department store prices. the function c(x) = 0.75x can be used to determine the cost c, in dollars, of an item, where x is the department store price, in dollars. if the item has not sold in one month, the discount store takes an additional 20% off the discounted price and an additional $5 off the total purchase. the function d(y) = 0.80y - 5 can be used to find d, the cost, in dollars, of an item that has not been sold for a month, where y is the discount store price, in dollars. create a function d(c(x)) that represents the final price of an item when a costumer buys an item that has been in the discount store for a month. d(c(x)) =
Answers: 1
You know the right answer?
Your boss estimates it take 42 person - hours to rearrange the floor plan for the produce department...