Write a system of equations to describe the situation below, solve using any method, and fill in the blanks.
Two road crews are paving a straight section of highway. The first crew has completed paving
97 kilometers and is completing 2 additional kilometers per day. The second crew has only
finished 70 kilometers but is covering 5 kilometers per day. If the two crews started at
opposite ends of the road and are working toward the middle, they will eventually meet. How
much road will each crew have completed? How long will that take?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:00, cferguson
Someone answer asap for ! the total ticket sales for a high school basketball game were $2,260. the ticket price for students were $2.25 less than the adult ticket price. the number of adult tickets sold was 230, and the number of student tickets sold was 180. what was the price of an adult ticket?
Answers: 1
image
Mathematics, 21.06.2019 21:00, itsdeevv
How many kilograms of a 5% salt solution and how many kilograms of a 15% salt solution must be mixed together to make 45kg of an 8% salt solution?
Answers: 3
image
Mathematics, 21.06.2019 22:30, xandraeden32
Ingredient c: 1/4 cup for 2/3 serving or ingredient d: 1/3 cup for 3/4 serving which unit rate is smaller
Answers: 2
image
Mathematics, 21.06.2019 23:00, janeou17xn
Mike wants to make meatloaf. his recipe uses a total of 8 pounds of meat. if he uses a 3 to 1 ratio of beef to pork, how much pork will he use? enter your answer as a mixed number in simplest terms.
Answers: 1
You know the right answer?
Write a system of equations to describe the situation below, solve using any method, and fill in t...

Questions in other subjects:

Konu
Biology, 18.12.2019 15:31
Konu
Physics, 18.12.2019 15:31