Choose the correct answer. The time to complete a project varies inversely with the number of employees. If 6 people can complete the project in 4 days, how long will it take 8 people?

A. 5 days
B. 3 days
C. 2 days
D. 6 days

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 20.06.2019 18:02, ParallelUniverse
Convert 16 yards to feet use the conversion rate 3 feet = 1 yard
Answers: 2
image
Mathematics, 21.06.2019 13:20, gobbler80
Part a what is the area of triangle i? show your calculation. part b triangles i and ii are congruent (of the same size and shape). what is the total area of triangles i and ii? show your calculation. part c what is the area of rectangle i? show your calculation. part d what is the area of rectangle ii? show your calculation. part e rectangles i and iii have the same size and shape. what is the total area of rectangles i and iii? show your calculation. part f what is the total area of all the rectangles? show your calculation. part g what areas do you need to know to find the surface area of the prism? part h what is the surface area of the prism? show your calculation. part i read this statement: “if you multiply the area of one rectangle in the figure by 3, you’ll get the total area of the rectangles.” is this statement true or false? why? part j read this statement: “if you multiply the area of one triangle in the figure by 2, you’ll get the total area of the triangles.” is this statement true or false? why?
Answers: 2
image
Mathematics, 21.06.2019 15:00, EatsChiken
Aformual for 8 bottles of window cleaner calls for 6 cups of rubbing to customers alcohol 2 1/4 gallons of water and 1 1/2 cups of ammonia alcohol would the forula call if a factory made 1,280 bottles for stores to sell to customers
Answers: 1
image
Mathematics, 21.06.2019 19:30, marvin07
Anna is constructing a line segment that is congruent to another segment ab. for the construction, which tool should be used to mesure segment ab
Answers: 1
You know the right answer?
Choose the correct answer. The time to complete a project varies inversely with the number of empl...

Questions in other subjects:

Konu
Mathematics, 18.03.2021 16:50
Konu
Mathematics, 18.03.2021 16:50
Konu
Mathematics, 18.03.2021 16:50
Konu
Mathematics, 18.03.2021 16:50