10 workers can paint a building in 21 days. If work has to be finished in 15 days, how many extra workers are required?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:30, purpletart41
Arrange these numbers from least to greatest 3/5 5/7 2/9
Answers: 2
image
Mathematics, 21.06.2019 15:30, LadyHolmes67
When i add money am i supposed to make it like this 7+12 or 7.00+12.00 because i got 19 dollars for my answer
Answers: 2
image
Mathematics, 21.06.2019 18:00, isaiahcannon5709
Use the data on the dot plot to answer the question. how many people read for more than three hours last week? i'm on a unit test review
Answers: 1
image
Mathematics, 21.06.2019 18:30, kaitie60
Which statement describes surface features called maria on the moon
Answers: 3
You know the right answer?
10 workers can paint a building in 21 days. If work has to be finished in 15 days, how many extra wo...

Questions in other subjects:

Konu
Mathematics, 29.03.2020 19:14
Konu
Biology, 29.03.2020 19:15