Mathematics, 09.12.2021 18:40 mattmaddox86

Una excavadora trabajando 10 horas al día abre una sequía de 1000 metros en 8 días. Cuanto tardaría en abrir una sequía de 600 metros si trabaja 12 horas al día?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:20, lagarde
Reflect the point (7,0) across the y-axis
Answers: 2
image
Mathematics, 21.06.2019 18:30, luvme68297
Which statement justifies why angle ebc measures 90?
Answers: 3
image
Mathematics, 22.06.2019 02:00, SoccerHalo
Milk and ice cream are mixed together for a recipe. the total volume of the mixture is 1 cup. if the milk contains 2% fat, the cream contains 18% fat ,and the mixture contains 6% fat ,how much cream is in the mixture
Answers: 1
image
Mathematics, 22.06.2019 03:30, xnadertheking
What is the benefit of converting measures in a ratio to the same unit
Answers: 1
You know the right answer?
Una excavadora trabajando 10 horas al día abre una sequía de 1000 metros en 8 días. Cuanto tardaría...

Questions in other subjects:

Konu
Social Studies, 01.12.2021 19:20
Konu
Mathematics, 01.12.2021 19:20
Konu
Mathematics, 01.12.2021 19:20