Company A needs 110 days to rebuild a bridge. Company B needs 150 days to rebuild the same bridge. Working together, they can do the job in d days. Which equation can be used to find the value of d?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:20, acharity196
Do social recommendations increase ad effectiveness? a study of online video viewers compared viewers who arrived at an advertising video for a particular brand by following a social media recommendation link to viewers who arrived at the same video by web browsing. data were collected on whether the viewer could correctly recall the brand being advertised after seeing the video. the results are given below. correctly recalled the brandarrival 409153browsing20484b. conduct the hypothesis test, using the 0.025 level of significance. what is the value of the test statistic? χ2stat=what is the p-value? p-value=is this value significant atα=0.025?
Answers: 2
image
Mathematics, 21.06.2019 18:40, wisal96
What value of x is in the solution set of 4x – 12 s 16 + 8x?
Answers: 3
image
Mathematics, 21.06.2019 19:30, janetexcoelho
Find the distance between (0,5) & (-4,2)
Answers: 1
image
Mathematics, 21.06.2019 21:30, byers024
‼️‼️‼️10 points‼️‼️‼️ me it’s important‼️‼️‼️‼️‼️
Answers: 1
You know the right answer?
Company A needs 110 days to rebuild a bridge. Company B needs 150 days to rebuild the same bridge. W...

Questions in other subjects: