On May 1, 2020, Swifty Corporation began construction of a building. Expenditures of $610800 were incurred monthly for 5 months beginning on May 1. The building was completed and ready for occupancy on September 1, 2020. For the purpose of determining the amount of interest cost to be capitalized, the weighted-average accumulated expenditures on the building during 2020 were $610800.
$3054000.
$2443200.
$509000.

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:50, jay4881
Which undefined geometric term is described as a location on a coordinate plane that is designed by an ordered pair (x, y) ?
Answers: 1
image
Mathematics, 21.06.2019 17:30, Justinoreilly71
The dolphins at the webster are fed 1/2 of a bucket of fish each day the sea otters are fed 1/2 as much fish as the dolphins how many buckets of fish are the sea fed each day? simplify you answer and write it as a proper fraction or as a whole or mixed number
Answers: 1
image
Mathematics, 21.06.2019 18:00, bandnerd1
In triangles abc and wxy, a=w and b=x which of the following must be true to prove abc=wxy by the aas theorem? a. ab=bc b. bc=xy c. ab=wx d.
Answers: 1
image
Mathematics, 21.06.2019 19:50, maggie3541
Math it's appreciated. (picture provided)
Answers: 1
You know the right answer?
On May 1, 2020, Swifty Corporation began construction of a building. Expenditures of $610800 were in...

Questions in other subjects:

Konu
Mathematics, 07.05.2020 07:58