The estimated project completion times ( days) for the Safaricom PLC Marketing research Assignment problem is as follows; REGION
PROJECT LEADER 1 2 3
Muthoni 10 15 9
Oduor 9 18 5
Toroitich 6 14 3
Required:
Draw a network model for the project
Develop the objective function
Conduct an optimal assignment of the three project leaders to the three regions using the Hungarian approach.
Comment on the results

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:10, donaldwilliams31
Given the function f(x) = log base 4(x+8) , find the value of f^-1(2)
Answers: 1
image
Mathematics, 21.06.2019 20:30, AllanCasey12
Angles r and s are complementary. the measure of angle r is 31 degrees. which equation can be used to find angle s?
Answers: 1
image
Mathematics, 21.06.2019 21:30, guill41
Write an equation of the line that passes through the point (2, 3) and is perpendicular to the line x = -1. a) y = 1 b) y = 3 c) y = 0 eliminate d) y = -3
Answers: 2
image
Mathematics, 21.06.2019 21:30, VETORRES
Find the volume of the solid obtained by rotating the region enclosed by the curves y=1x and y=7^-x about the x-axis. (use symbolic notation and fractions where needed.) volume =
Answers: 3
You know the right answer?
The estimated project completion times ( days) for the Safaricom PLC Marketing research Assignment p...

Questions in other subjects:

Konu
History, 12.01.2021 22:00
Konu
History, 12.01.2021 22:00
Konu
Mathematics, 12.01.2021 22:00
Konu
Mathematics, 12.01.2021 22:00
Konu
Biology, 12.01.2021 22:00