When building a house, the number of days required to build varies inversely with with the number of workers. One house was built in 20
days by 19 workers. How many days would it take to build a similar
house with 38 workers?

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:20, lizziesuks
At the newest animated movie, for every 9 children, there are 4 adults. there are a total of 39 children and adults at the movie.
Answers: 2
image
Mathematics, 21.06.2019 23:30, amayax77
Find │–14│ a. 14 b. –14 c. start fraction 1 over 14 end fraction
Answers: 2
image
Mathematics, 22.06.2019 00:00, meganwintergirl
Can someone plz me understand how to do these. plz, show work. in exercises 1-4, rewrite the expression in rational exponent form.[tex]\sqrt[4]{625} \sqrt[3]{512} (\sqrt[5]{4} )³ (\sqrt[4]{15} )^{7}\\ (\sqrt[3]{27} )^{2}[/tex]
Answers: 3
image
Mathematics, 22.06.2019 00:10, zarbyp30
Given: p: 2x = 16 q: 3x – 4= 20 which is the converse of p - q? if 2x + 16, then 3x - 4 20. if 3x –4 +20, then 2x # 16. lf 2x = 16, then 3x - 4 = 20. lf 3x – 4= 20, then 2x = 16. o o
Answers: 1
You know the right answer?
When building a house, the number of days required to build varies inversely with with the number o...

Questions in other subjects: