Explain why the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks orless.

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, camila9022
Can someone answer it, and plot it, for 20 points and brainliest answer? p. s. they're the same ! : )
Answers: 1
image
Mathematics, 21.06.2019 18:30, daidai123
Players on the school soccer team are selling candles to raise money for an upcoming trip. each player has 24 candles to sell. if a player sells 4 candles a profit of$30 is made. if he sells 12 candles a profit of $70 is made. determine an equation to model his situation?
Answers: 3
image
Mathematics, 21.06.2019 19:50, gymnastattack
Drag each tile into the correct box. not all tiles will be used. find the tables with unit rates greater than the unit rate in the graph. then tenge these tables in order from least to greatest unit rate
Answers: 2
image
Mathematics, 22.06.2019 01:20, stastnylindsey
Write 5 in the form of a/b using integers to show it as a rational number
Answers: 1
You know the right answer?
Explain why the probability that the critical path will be finished in 22 weeks or less is not neces...

Questions in other subjects:

Konu
Social Studies, 30.10.2020 16:50
Konu
Mathematics, 30.10.2020 16:50