Mathematics, 08.06.2021 17:20 24elkinsa

Company A can produce 200 basketballs in 3 days while Company B can produce 250 basketballs in 4 days. If the two companies joined forces, how many days would it take them to produce 2,000 basketballs? A. about 13 days B. about 15 days C. about 11 days D. about 17 days

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 22.06.2019 00:00, mkay78
Apassenger train and a freight train leave san jose at 3pm, traveling in the same direction. the passenger train is going three times as fast as the freight train. at 6pm they are 240 miles apart. how fast is each travelling? explain your answer and show your
Answers: 1
image
Mathematics, 22.06.2019 01:00, mdegracia73
The actual length of side t is 0.045cm. use the scale drawing to find the actual side length of w
Answers: 1
image
Mathematics, 22.06.2019 01:50, QueensQueens
Lesson 9-3 for items 8-10, a square is drawn in the coordinate plane, with vertices as shown in the diagram. then the square is reflected across the x-axis. -2 4 8. the function that describes the reflection is (x, y) - a. (x, y-3). b. (x, y-6). c. (-x, y). d. (x,- y).
Answers: 2
image
Mathematics, 22.06.2019 03:00, milkshakegrande101
The formula for finding volume of a cone 1/3pi x r^2h. the volume of a cone is 300 cm^3 and the height of the cone is 10 what is the approximate radius of the cone
Answers: 1
You know the right answer?
Company A can produce 200 basketballs in 3 days while Company B can produce 250 basketballs in 4 day...

Questions in other subjects:

Konu
Spanish, 11.09.2020 22:01
Konu
German, 11.09.2020 22:01
Konu
Mathematics, 11.09.2020 22:01
Konu
Mathematics, 11.09.2020 22:01
Konu
Mathematics, 11.09.2020 22:01
Konu
Mathematics, 11.09.2020 22:01
Konu
Chemistry, 11.09.2020 22:01
Konu
Social Studies, 11.09.2020 22:01
Konu
English, 11.09.2020 22:01
Konu
Mathematics, 11.09.2020 22:01