48 men were deployed to construct a bridge in 30 days. (a) By letting the number of men be m and the number of days needed to complete the
construction works be d, form an equation relating m and d.
(b) After 10 days, 8 men were sent to help in another project, how many days will the
construction work be delayed, assuming that all the men work at the same rate?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 12:30, savannahvargas512
The highest common factor of 132 and 220
Answers: 1
image
Mathematics, 21.06.2019 15:40, hannahkharel2
What is a rational number between 9.5 and 9.7
Answers: 3
image
Mathematics, 21.06.2019 21:30, coontcakes
Acd that is originally priced at $15.85 red-tagged for the sale. what is the sale price of the cd
Answers: 1
image
Mathematics, 21.06.2019 23:30, Ab20600
Plzzz answer both questions and i will give you 100 points
Answers: 1
You know the right answer?
48 men were deployed to construct a bridge in 30 days. (a) By letting the number of men be m and th...

Questions in other subjects:

Konu
Mathematics, 25.11.2021 14:00