When building a house, the number of days required to build varies inversely with
with the number of workers. One house was built in 11 days by 49 workers. How
many days would it take to build a similar house with 7 workers?
Answers: 2
Mathematics, 21.06.2019 15:00, thegent1859
This is the number of parts out of 100, the numerator of a fraction where the denominator is 100. submit
Answers: 3
Mathematics, 21.06.2019 17:00, beautycutieforever10
Evaluate the expression for the given value of the variable. 5×(h+3) for h=7
Answers: 1
Mathematics, 21.06.2019 20:00, soph10131
M the table below represents a linear function f(x) and the equation represents a function g(x): x f(x)−1 −50 −11 3g(x)g(x) = 2x − 7part a: write a sentence to compare the slope of the two functions and show the steps you used to determine the slope of f(x) and g(x). (6 points)part b: which function has a greater y-intercept? justify your answer. (4 points)
Answers: 3
Mathematics, 21.06.2019 21:00, carissaprocacci
Tessa bought stock in a restaurant for $253.00. her stock is now worth $333.96. what is the percentage increase of the value of tessa's stock? a.) 81% b.) 32% c.) 24% d.) 76%
Answers: 1
When building a house, the number of days required to build varies inversely with
with the number o...
Mathematics, 20.09.2020 04:01
Mathematics, 20.09.2020 04:01
Mathematics, 20.09.2020 04:01
History, 20.09.2020 04:01