Q11
Eight bricklayers on a building site took 25 hours to build a wall.
The Site Manager need...
Mathematics, 26.05.2021 23:50 dyllanmasters99
Q11
Eight bricklayers on a building site took 25 hours to build a wall.
The Site Manager needs a similar wall built.
He can hire five bricklayers to build this wall.
He needs to know how much longer it will take to build this wall.
How much longer will it take?
Answers: 1
Mathematics, 21.06.2019 17:00, a897coleman
One month, a music site observed that 60% of the people who downloaded songs from its site downloaded q sam's latest single. the equation below represents this information, where x represents the total number of people who ddownloaded songs from the site that month: x = 0.6x + 384 how many people who downloaded songs from the site that month downloaded q sam's latest single?
Answers: 3
Mathematics, 21.06.2019 21:50, kaylaamberd
Suppose that the price p, in dollars, and the number of sales, x, of a certain item follow the equation 4 p plus 4 x plus 2 pxequals56. suppose also that p and x are both functions of time, measured in days. find the rate at which x is changing when xequals2, pequals6, and startfraction dp over dt endfraction equals1.5.
Answers: 2
Computers and Technology, 07.11.2020 01:40
Social Studies, 07.11.2020 01:40
Mathematics, 07.11.2020 01:40
Chemistry, 07.11.2020 01:40