Your manufacturing requires parts to go sequentially through process A, B, and C. A machine can do process A in 1 minute, B in 2 minutes, and C in 3 minutes. You have two A machines, one B machine, and three C machines. Which process is the
bottleneck (can produce the fewest items per unit time)?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:00, taehyungg
Which fraction is not equivalent to 8/12 a. 2/3 b. 24/36 c. 4/10 d. 6/10
Answers: 1
image
Mathematics, 22.06.2019 00:50, india336
To diagonalize an nxn matrix a means to find an invertible matrix p and a diagonal matrix d such that a pdp d p ap or [1 3 dh epap 3 let a=-3 -5 -3 3 3 1 step 1: find the eigenvalues of matrix a "2's" step 2: find the corresponding eigenvectors of a step 3: createp from eigenvectors in step 2 step 4 create d with matching eigenvalues.
Answers: 3
image
Mathematics, 22.06.2019 01:30, xojade
The population of a bacteria colony grows by a consistent percentage each hour and can be modeled by the function y = 500(1.16)t. what does the value 500 represent in the function?
Answers: 2
image
Mathematics, 22.06.2019 02:00, emaleyhughes21
16x^2-16x=5 solve the equation by completing the square
Answers: 3
You know the right answer?
Your manufacturing requires parts to go sequentially through process A, B, and C. A machine can do p...

Questions in other subjects:

Konu
Mathematics, 28.12.2019 02:31