A 18 -person road crew is scheduled to finish repairing a highway in 10 days. On the morning of the fifth day, several workers of the crew were moved to another project. How many workers were removed from the crew, if the rest of the crew finished the remaining repairs in 12 days?
Answers: 1
Mathematics, 21.06.2019 19:10, brownzackery71
Girardo is using the model below to solve the equation . girardo uses the following steps: step 1 add 4 negative x-tiles to both sides step 2 add 1 negative unit tile to both sides step 3 the solution is which step could be adjusted so that gerardo's final step results in a positive x-value? in step 1, he should have added 4 positive x-tiles to both sides. in step 1, he should have added 3 negative x-tiles to both sides. in step 2, he should have added 4 negative unit tiles to both sides. in step 2, he should have added 1 positive unit tile to both sides.
Answers: 2
Mathematics, 21.06.2019 21:30, InvictusPain4777
Yo need asap pls ! markin da brainiest too !
Answers: 1
A 18 -person road crew is scheduled to finish repairing a highway in 10 days. On the morning of the...
Mathematics, 22.01.2021 23:50
Chemistry, 22.01.2021 23:50
Social Studies, 22.01.2021 23:50
Geography, 22.01.2021 23:50