The amount of workers varies inversely with the time, in days, to complete a project. Five workers can complete a certain project in 24 days. How many workers will be needed to complete the project in 15 days?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, Hfruit
You drop a rubber ball off the roof of a 50 meter high building onto a paved parking lot. it bounces back up with every bounce, but not quite all the way back up to you. after the first bounce it bounces back only 80 percent of the distance it was dropped from. the pattern continues, meaning after every bounce it comes up to just 80 percent of the previous maximum height. so if before the first bounce the height is 50 meters, what height does the ball reach after the fifth bounce? round your answer to one decimal place and chose the correct response from the choices below:
Answers: 1
image
Mathematics, 21.06.2019 18:30, nina288
Astuntman jumping off a 20-m-high building is modeled by the equation h=20-5t^2, where t is the same in seconds. a high-speed camera is ready to film him between 15m and 10m above the ground. for which interval of time should the camera film him?
Answers: 1
image
Mathematics, 21.06.2019 18:30, 59279
Which equation represents the model shown? a)1/3 divide 1/6 = 2 b)2/3 divide 1/6 = 2/18 c)1/3 divide 1/6 = 1/18 d)2/3 divide 1/6 =4
Answers: 1
image
Mathematics, 21.06.2019 20:30, corbeansbrain
Someone answer asap for ! michele pushes a box d meters across a floor. she uses a force f, in newtons, to push the box. she pushes the box for t seconds. the formula p = fd/t calculates the power, p, in watts, that it takes for michele to complete the task. solve the formula for d.
Answers: 2
You know the right answer?
The amount of workers varies inversely with the time, in days, to complete a project. Five workers c...

Questions in other subjects:

Konu
Computers and Technology, 17.03.2021 23:40
Konu
Mathematics, 17.03.2021 23:40