There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. what is the probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, neariah24
Abox of chocolates costs $7. which equation relates the number of boxes sold (x) and total cost of the boxes sold (y)?
Answers: 2
image
Mathematics, 21.06.2019 17:40, JordanJones04402
Given f(x)= 9x+1 and g(x)=x^3, choose the expression (f*g)(x)
Answers: 2
image
Mathematics, 21.06.2019 19:00, issaaamiaaa15
You got a job selling magazines door-to-door. you are paid $100 per day plus $1.50 for each magazine you sell. which recursive formula models this situation?
Answers: 1
image
Mathematics, 22.06.2019 00:20, arianasg06
When steve woke up. his temperature was 102 degrees f. two hours later it was 3 degrees lower. what was his temperature then?
Answers: 3
You know the right answer?
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2....

Questions in other subjects:

Konu
Mathematics, 25.02.2020 05:13
Konu
Mathematics, 25.02.2020 05:13