The following is a table of activities associated with
a project at rafay ishfaq’s software firm in chicago, their durations,
and what activities each must precede:
activity duration (weeks) precedes
a (start) 1 b, c
b 1 e
c 4 f
e 2 f
f (end) 2 —
a) draw an aon diagram of the project, including activity durations.
b) define the critical path, listing all critical activities in chronological
order.
c) what is the project duration (in weeks)?
d) what is the slack (in weeks) associated with any and all noncritical
paths through the project?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:50, queenkendra16
Which expression is equivalent to 4 square root 6 divided by 3 root 2
Answers: 1
image
Mathematics, 21.06.2019 17:00, Geo777
Suppose a pendulum is l meters long. the time, t,in seconds that it tales to swing back and forth once is given by t=2.01
Answers: 1
image
Mathematics, 21.06.2019 17:00, eazywalters
There is a spinner with 14 equal areas, numbered 1 through 14. if the spinner is spun one time, what is the probability that the result is a multiple of 2 or a multiple of 5?
Answers: 2
image
Mathematics, 21.06.2019 19:30, astigall6360
Asap! i'm not good math and i'm lost.
Answers: 2
You know the right answer?
The following is a table of activities associated with
a project at rafay ishfaq’s software fi...

Questions in other subjects:

Konu
Physics, 11.01.2022 05:00
Konu
Mathematics, 11.01.2022 05:10
Konu
Mathematics, 11.01.2022 05:10