Mathematics, 19.04.2021 04:00 serg42

The number of days needed pave a section of high way varies inversely as the number of people working on the job. It takes 18days for 2 people to complete the project. If the job has to be finished in 4 days how many people are needed? ​

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:30, miracle96
Choose the more precise measurement. 26.4 cm or 8.39 cm
Answers: 1
image
Mathematics, 21.06.2019 21:30, jeanm
Having a hard time understanding this question (see attachment).
Answers: 2
image
Mathematics, 21.06.2019 22:30, monkemily1
There are 93 calories in a small candy bar how many calories are ther in a half dozen small candy bars?
Answers: 2
image
Mathematics, 22.06.2019 00:30, haileybug0305
Brent paid for 6 avocados with a $20.00 bill. he received $10.40 in change. construct and solve an equation can be used to find the price , of each avocados
Answers: 1
You know the right answer?
The number of days needed pave a section of high way varies inversely as the number of people workin...