Mathematics, 24.08.2019 05:00 maria051002camp

The time it takes to lay a sidewalk of a certain type varies directly as the length and inversely as the number of men working. if eight men take two days to lay 100 feet, how long will three men take to lay 150 feet?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 21:30, izabelllreyes
Look at triangle wxy what is the length (in centimeters) of the side wy of the triangle?
Answers: 2
image
Mathematics, 21.06.2019 22:30, madisonwr
Nicole is making carrot bread she needs 5 cups of carrots for 2 cups of sugar. what is the ratio of cups of sugar to cups of carrots that nicole will need? write the ration in three different ways
Answers: 1
image
Mathematics, 21.06.2019 23:00, kealalac1
Afunction, f(x), represents the height of a plant x months after being planted. students measure and record the height on a monthly basis. select the appropriate domain for this situation. a. the set of all positive real numbers b. the set of all integers oc. the set of all positive integers od. the set of all real numbers reset next
Answers: 3
image
Mathematics, 21.06.2019 23:00, dianereyes7475
The angles in a triangle are represented by 5x, 8x, and 2x+9. what is the value of ? a.10.8 b.11.4 c.9.7 d.7.2
Answers: 2
You know the right answer?
The time it takes to lay a sidewalk of a certain type varies directly as the length and inversely as...

Questions in other subjects:

Konu
Mathematics, 09.04.2021 20:10
Konu
Mathematics, 09.04.2021 20:10