The Loetschberg tunnel was built to connect Bern, Switzerland, with the ski resorts in the southern
Swiss Alps. This was accomplished by the Swiss using one engineering company that started at the
north end and another company that started at the south end. Suppose the company at the north end
could drill the entire tunnel in 22.2 years and south company could do it in 21.8 years. How long would
it have taken the two companies to drill the tunnel?
![ansver](/tpl/images/cats/User.png)
Answers: 3
![](/tpl/images/ask_question.png)
![](/tpl/images/ask_question_mob.png)
Other questions on the subject: Mathematics
![image](/tpl/images/cats/mat.png)
![image](/tpl/images/cats/mat.png)
Mathematics, 21.06.2019 19:00, aceves5493
After t seconds, a ball tossed in the air from the ground level reaches a height of h feet given by the equation h = 144t-16t^2. after how many seconds will the ball hit the ground before rebounding?
Answers: 2
You know the right answer?
The Loetschberg tunnel was built to connect Bern, Switzerland, with the ski resorts in the southern...
Questions in other subjects:
![Konu](/tpl/images/cats/mat.png)
Mathematics, 19.10.2021 01:00
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/mat.png)
Mathematics, 19.10.2021 01:00
![Konu](/tpl/images/cats/User.png)
![Konu](/tpl/images/cats/himiya.png)
Chemistry, 19.10.2021 01:00
![Konu](/tpl/images/cats/ekonomika.png)
![Konu](/tpl/images/cats/obshestvoznanie.png)
Social Studies, 19.10.2021 01:00
![Konu](/tpl/images/cats/User.png)
SAT, 19.10.2021 01:00