Mathematics, 18.03.2021 01:50 jahzz

The expected activity time in PERT analysis is calculated as: the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b. the sum of the optimistic, pessimistic, and most likely times, divided by six. the simple average of the optimistic, pessimistic, and most likely times. the sum of the activity variances, divided by six. the sum of the optimistic, pessimistic, and most likely times.

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 16:30, enchantednights
Look at attachment. has all info needed. need
Answers: 1
image
Mathematics, 21.06.2019 19:00, Goldenstate32
Gh bisects fgi. find the measure of hgi •15° •21° •10° •8°
Answers: 2
image
Mathematics, 21.06.2019 21:10, linettepizarro1233
See attachment below and find the equivalent of tan(∠qsr)
Answers: 3
image
Mathematics, 21.06.2019 23:00, shawdyylinda
The architect's side view drawing of a saltbox-style house shows a post that supports the roof ridge. the support post is 8 ft tall. the distance from the front of the house to the support post is less than the distance from the post to the back of the house. how far from the front of the house is the support post positioned?
Answers: 1
You know the right answer?
The expected activity time in PERT analysis is calculated as: the weighted average of a, m, and b, w...

Questions in other subjects:

Konu
History, 14.04.2020 18:05