UP Inc. is building an annex for their data processing system. The cost of the annex is $1,750,000. The architect they hired charges 6.5% of the cost
of the annex. The systems analyst charges a flat fee of $10,000. The
computer programmer charges $45 per hour and will work for 80 hours.
What is the total cost of the professional services?

What’s the answer

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:30, kordejah348
Atriangle with all sides of equal length is a/an triangle. a. right b. scalene c. equilateral d. isosceles
Answers: 2
image
Mathematics, 21.06.2019 18:30, angelina6836
Anormally distributed data set has a mean of 176.3 and a standard deviation of 4.2. what is the approximate z-score for the data value of 167.9? 2.00 −2.00 8.4 −8.4
Answers: 2
image
Mathematics, 21.06.2019 19:00, love123jones
Explain why the factor 1.5 is broke. into two numbers in the model.
Answers: 3
image
Mathematics, 21.06.2019 20:30, Mgarcia325
Justin has 750 more than eva and eva has 12 less than justin together they have a total of 63 how much money did
Answers: 1
You know the right answer?
UP Inc. is building an annex for their data processing system. The cost of the annex is $1,750,000....

Questions in other subjects:

Konu
Mathematics, 13.12.2019 06:31
Konu
Mathematics, 13.12.2019 06:31