Mathematics, 11.03.2021 20:50 dannaasc5475

7070 To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?
o

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:00, mixedkiddo
The two square pyramids are similar. find the total volume of both pyramids if the ratio of their surface areas is 9/16
Answers: 3
image
Mathematics, 21.06.2019 21:00, cicimarie2018
Choose the equation that represents the graph below: (1 point) graph of a line passing through points negative 3 comma 0 and 0 comma 3 y = x − 3 y = −x + 3 y = −x − 3 y = x + 3 will award !
Answers: 3
image
Mathematics, 22.06.2019 04:40, robert7248
4. jake needs to score in the top 10% in order to earn a physical fitness certificate. the class mean is 78 and the standard deviation is 5.5. what raw score does he need? z value for top 10% =1.282 how do i get the z value? what is the equation for this? raw score =mean+z*sd = 78+1.282*5.5 = 85.051
Answers: 3
image
Mathematics, 22.06.2019 05:30, mike2910
Robert plans to make a box-and-whisker plot of the following set of data. 27, 14, 46, 38, 32, 18, 21 find the lower quartile, the median, and the upper quartile of the set? lower quartile: 19.5; median: 29.5; upper quartile: 42 lower quartile: 14; median: 27; upper quartile: 46 lower quartile: 18; median: 27; upper quartile: 38 lower quartile: 16; median: 29.5; upper quartile: 42
Answers: 1
You know the right answer?
7070 To complete a task in 16 days a company needs
5 people each working for 6 hours per day....

Questions in other subjects:

Konu
Mathematics, 29.07.2020 17:01