if the construction of a certain school is not completed by the agree upon date the contractor pays penalty of birr 1000 for the first week ,birr 2000 for the second week ,birr 3000 for the third week and so on that is overdue if construction of the school is completed 13 week late calculate the total amount of the penalties that the contractor must pay ?