Mathematics, 02.03.2021 21:30 morganzahn16

El ingeniero Luna desea construir un edificio con la ayuda de 20 albañiles en un lapso de 320 días. Si al dueño del edificio le urge que sea en el menor tiempo posible, ¿cuántos albañiles tendrá que contratar el ingeniero Luna para terminarlo en 200 días?

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, wbrandi118
Solve the equation x/4 - 5= -8 -27 -12 -7 12
Answers: 2
image
Mathematics, 21.06.2019 20:40, anaruiz00
What are the values of each variable in the diagram below?
Answers: 2
image
Mathematics, 22.06.2019 00:30, atran6955
The graph of f(x) is obtained by reflecting the graph of f(x)=-3|x| over the x-axis. which equation describes f(x)? a) f(x)=3|x| b) f(x)=|x+3| c) f(x)=-3|x| d) f(x) = - |x+3|
Answers: 1
image
Mathematics, 22.06.2019 01:00, triddi666
Two trains leave stations 546 miles apart at the same time and travel toward each other. one train travels at 95 miles per hour while the other travels at 115 miles per hour l. how long will it take for the two trains to meet
Answers: 3
You know the right answer?
El ingeniero Luna desea construir un edificio con la ayuda de 20 albañiles en un lapso de 320 días....