Megan's team is comprised of 10 people who work for 40 hours per week. The team is tasked with completing a project that requires 700-man hours in one week. To complete the project Megan plans to add members to the team and have each team member work an extra 3n hours that week. What is the minimum number of extra team member she needs?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 20:30, cheating53
Kayaks rent for $35 per day. which expression can you use to find the cost in dollars of renting 3 kayaks for a day?
Answers: 1
image
Mathematics, 21.06.2019 20:30, Courtneymorris19
Barney & noblet customers can choose to purchase a membership for $25 per year members receive 10% off all store purchases 1. how much would a member pay per year if he bought $50 worth of items each year? 2. write a slope-intercept equation that expresses how much a member pays per year using x to represent his purchases per year 3. how much would a member have to spend per year to pay off his membership fee?
Answers: 1
image
Mathematics, 21.06.2019 21:00, trinitymarielouis
How do you write y-10=2 (x-8) in standard form
Answers: 1
image
Mathematics, 21.06.2019 22:30, owlette2001
50 points~ ! i have to turn this in tomarrow
Answers: 2
You know the right answer?
Megan's team is comprised of 10 people who work for 40 hours per week. The team is tasked with compl...

Questions in other subjects: