Please help me I’ll give you brainliest and thanks please it’s due in 20 minutes
...
Mathematics, 23.02.2021 21:20 clara384
Please help me I’ll give you brainliest and thanks please it’s due in 20 minutes
Answers: 2
Mathematics, 21.06.2019 21:30, mandyangle01
Using pert, adam munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4. a) what is the probability that the project will be completed in 17 months? b) what is the probability that the project will be completed in 20 months? c) what is the probability that the project will be completed in 23 months? d) what is the probability that the project will be completed in 25 months? e) what is the due date that yields a 95% chance of completion?
Answers: 3
Computers and Technology, 24.07.2019 02:20