This exercise illustrates that poor quality can affect schedules and costs. A manufacturing process has 90 customer orders to fill. Each order requires one component part that is purchased from a supplier. However, typically, 3% of the components are identified as defective, and the components can be assumed to be independent.
Required:
a. If the manufacturer stocks 90 components, what is the probability that the 90 orders can be filled without reordering components?
b. If the manufacturer stocks 102 components, what is the probability that the 100 orders can be filled without reordering components?
c. If the manufacturer stocks 105 components, what is the probability that the 100 orders can be filled without reordering components?
Answers: 1
Mathematics, 21.06.2019 18:30, jamalnellum56
The square pyramid has a volume of 441 cubic inches. what is the value of x? 1/7x is the height x is the base
Answers: 2
Mathematics, 22.06.2019 00:00, samafeggins2
Lana's family entered a 5-kilometer race lana's average step length is about 0.5 meter how many steps will she need to take the finish
Answers: 1
This exercise illustrates that poor quality can affect schedules and costs. A manufacturing process...
Mathematics, 28.03.2021 08:30
Mathematics, 28.03.2021 08:30
Mathematics, 28.03.2021 08:30
Mathematics, 28.03.2021 08:30