A factory process requires 3 steps to finish a product. The steps each have a mean completion time of A= 10 seconds and a standard deviation of o = 5 seconds. The time it takes to complete each step is independent from the other steps. Let T be the total completion time for the 3 steps.
Find the standard deviation of T.
Choose 1
OT = 15 seconds
Or = 75 seconds
or 15 seconds
or = v75 seconds
Answers: 2
Mathematics, 21.06.2019 14:00, williams5847
Chanelle deposits $7,500 into the bank. she does not withdraw or deposit money for 6 years. she earns 6% interest during that time. what will the balance be when she is finally able to withdraw her money?
Answers: 1
Mathematics, 21.06.2019 21:30, mrlepreqon8897
Apool measures 100 meters by 100 meters a toddler inside the pool and trows a ball 60 centimeters from one edge of the pool. how far is the ball from the opposite edge of the pool
Answers: 1
Mathematics, 21.06.2019 21:40, chunkymonkey090
Ihonestly have no clue if it's each or none.
Answers: 1
A factory process requires 3 steps to finish a product. The steps each have a mean completion time o...
Mathematics, 20.08.2020 08:01
History, 20.08.2020 08:01
Mathematics, 20.08.2020 08:01
Mathematics, 20.08.2020 08:01
Mathematics, 20.08.2020 08:01
History, 20.08.2020 08:01
Computers and Technology, 20.08.2020 08:01