It takes 6 labourers 7 days to complete a job. How many labourers would it take to complete the job in 3 days? I
labourers

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:40, kingteron6166
Which system of linear inequalities is represented by the graph? !
Answers: 1
image
Mathematics, 21.06.2019 16:30, danielmurillo28
If c(x) = 4x – 2 and d(x) = x2 + 5x, what is (cxd)(x)
Answers: 2
image
Mathematics, 21.06.2019 20:30, PatienceJoy
If there is 20 dogs in the shelter and 5 dogs get homes, and then 43 more dogs come. how many dogs are there in the shelter?
Answers: 1
image
Mathematics, 21.06.2019 22:30, mackenzie27717
3. a sum of $2700 is to be given in the form of 63 prizes. if the prize is of either $100 or $25, find the number of prizes of each type.
Answers: 1
You know the right answer?
It takes 6 labourers 7 days to complete a job. How many labourers would it take to complete the job...

Questions in other subjects:

Konu
Health, 26.01.2021 22:20