Mathematics, 31.01.2021 16:00 privise
15 men can finish a piece of work in 40 days. How many more men should be added so that the work will be finished in 30 days?
Answers: 1
Mathematics, 21.06.2019 15:00, DerikF9478
Saline iv fluid bags cost $64.20 for 24, 1000 ml bags from one supplier. another supplier sells 500 ml bags for $2 each. the hospital uses about 10,000, 1000 ml bags each month. nurses report that about half of the bags are more than half full when they are discarded. if you are going to use only one supplier, which would you choose and how much would you save with that choice? show calculator try it! if you buy 1000 ml bags, how many do you need to buy each month? type your answer in the space provided and click on the check answer button.
Answers: 3
Mathematics, 21.06.2019 23:40, asiababbie33
Agrid shows the positions of a subway stop and your house. the subway stop is located at (-5,2) and your house is located at (-9,9). what is the distance, to the nearest unit, between your house and the subway stop?
Answers: 1
Mathematics, 22.06.2019 02:00, powella033
Acompound inequality is graphed, and its graph consists of all real numbers. which open scentence could have resulted in this solution set r> 3 or r< -2. r< 3 or r< -2. r> 3 or r> -2. r< 3 or r> -2 plz asap
Answers: 1
15 men can finish a piece of work in 40 days. How many more men should be added so that the work wil...
Physics, 29.07.2019 14:00
Mathematics, 29.07.2019 14:00
Arts, 29.07.2019 14:00
Biology, 29.07.2019 14:00