The project scheduling tool PERT (Program Evaluation and Review Technique) assumes a beta probability distribution for time
estimates. Which is NOT one of the three time estimates the model uses to calculate expected completion time?
les)
A)
Optimistic Time
B)
Most Likely Time
Least Likely Time
D)
Pessimistic Time
Answers: 2
Mathematics, 21.06.2019 20:00, jortizven0001
Seymour is twice as old as cassandra. if 16 is added to cassandra’s age and 16 is subtracted from seymour’s age, their ages become equal. what are their present ages? show !
Answers: 1
Mathematics, 21.06.2019 21:50, heavendl13
Which equation shows the quadratic formula used correctly to solve 5x2 + 3x -4 0 for x? cos -3+ v (3) 2-4() 2(5) 3+ |(3)² +4() 205) 3+ (3) 2-4() -3+ v (3)² +4()
Answers: 1
Mathematics, 22.06.2019 05:30, ashliemallen
The equation of line e is y = -4/9x + 5/6. line f is parallelto line e. what is the slope of line f
Answers: 1
The project scheduling tool PERT (Program Evaluation and Review Technique) assumes a beta probabilit...
Mathematics, 20.09.2019 21:00
Mathematics, 20.09.2019 21:00
Mathematics, 20.09.2019 21:00
Mathematics, 20.09.2019 21:00
Social Studies, 20.09.2019 21:00
Mathematics, 20.09.2019 21:00