A construction team gives an estimate of three months to repave a large stretch of a very busy road with their core crew of 9 people. The government responds that it is too much of an inconvenience to have this busy road obstructed for three months, so the job must be completed in one month. If the relationship between construction time and crew members is inversely proportional, how many crew members does the construction team need if they are to complete the job in one month

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:30, mustachegirl311
Use the multiplier method to incrases £258 by 43%
Answers: 1
image
Mathematics, 21.06.2019 22:00, Mgarcia325
Apackage of five erasers cost 0. $.39 at this rate how many how much would 60 erasers cost in dollars and cents
Answers: 2
image
Mathematics, 21.06.2019 22:00, JNH16
The numbers on a football field indicate 10 yard increments. you walk around the perimeter of a football field between the pylons. you walk a distance of 30623 yards. find the area and perimeter of the indicated regions. write your answers as mixed numbers, if necessary. a. one end zone: perimeter: yd area: yd2 b. the playing field (not including end zones): perimeter: yd area: yd2 c. the playing field (including end zones): perimeter: yd area: yd2
Answers: 1
image
Mathematics, 21.06.2019 23:00, esme72
Acompany made a profit of 75000 over a period of 6 years on an initial investment of 15000 what is the annual roi
Answers: 1
You know the right answer?
A construction team gives an estimate of three months to repave a large stretch of a very busy road...

Questions in other subjects:

Konu
Mathematics, 03.12.2021 02:50
Konu
English, 03.12.2021 02:50
Konu
Mathematics, 03.12.2021 02:50