a group of 4 pupils can take 2 weeks to do a certain job. how long will 12 pupils take to complete the job if they work at the same rate

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:00, coopera1744
Answer this question! 30 points and brainliest! only if you know the answer.
Answers: 1
image
Mathematics, 21.06.2019 21:30, vaelriacb5317
Is triangle jkl congruent to triangle rst? if so, what is the scale factor?
Answers: 1
image
Mathematics, 21.06.2019 22:20, jimena15
As voters exit the polls, you ask a representative random sample of voters if they voted for a proposition. if the true percentage of voters who vote for the proposition is 63%, what is the probability that, in your sample, exactly 5 do not voted for the proposition before 2 voted for the proposition? the probability is
Answers: 2
image
Mathematics, 21.06.2019 23:00, enca2619
If you apply the changes below to the linear parent function f(x)=x what is the equation of the new function vertically stretched by a factor of 3 flip over the x axis
Answers: 2
You know the right answer?
a group of 4 pupils can take 2 weeks to do a certain job. how long will 12 pupils take to complete t...

Questions in other subjects:

Konu
Mathematics, 21.09.2020 14:01