A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days 4/7 of the work is complete. How many additional men may be employed so that the work may b completed in time, each man now working 9 hours a day
Answers: 2
Mathematics, 21.06.2019 18:00, burnsmykala23
Solve this system of equations. 12x − 18y = 27 4x − 6y = 10
Answers: 1
Mathematics, 21.06.2019 19:50, Sourcandy
Organic apples are on special for $1.50 per pound. does total cost vary inversely or directly with the number of pounds purchased? find the cost of 3.4 pounds of apples. a. inversely: $5.10 b. directly; $5.10 c. inversely: $2.27 d. directly; $2.27
Answers: 1
Mathematics, 21.06.2019 22:00, wazzuphottie1999
Iam at home. /: i am playing video games. translate the following statement into symbolic form.
Answers: 2
A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. A...
English, 15.10.2019 11:30
Mathematics, 15.10.2019 11:30
Mathematics, 15.10.2019 11:30
Mathematics, 15.10.2019 11:30