A tower was built in 5,500 worker-hours. The contractor believes that the learning rate per tower will be 0.80 for additional towers. How many towers will have to be built before the time per tower is reduced to 3,000 worker-hours. How much time will be required for the 16th tower

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 15:40, Prettygirlbuggy
Two parallel lines are crossed by a transversal. what is the value of x? x = 40 x = 70 x = 110 x = 130
Answers: 2
image
Mathematics, 21.06.2019 18:00, DominaterDreemurr
In the polynomial below, what number should replace the question mark to produce a difference of squares? x2 + ? x - 36
Answers: 3
image
Mathematics, 21.06.2019 20:20, helpmeplzandty
Select the correct answer. what is the exact value of sin (157.5°)? a. 'sqrt(2 - sqrt(2))/2 b. *"-"'sqrt(2 + sqrt(2))/29 c.'sqrt(2 + sqrt(2))/4" d. "-"sqrt(2 + sqrt(2))/4)
Answers: 3
image
Mathematics, 21.06.2019 21:30, amandaaaa13
Find the ratios of the corresponding sides
Answers: 2
You know the right answer?
A tower was built in 5,500 worker-hours. The contractor believes that the learning rate per tower wi...

Questions in other subjects:

Konu
Mathematics, 04.03.2021 02:20