a field can be cleared by 33 men in 15days. how many more person required if the field has to be cleared 4 days earlier?

ansver
Answers: 3

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:40, bankskry
That table shows measurements (in invhes$ from cubes with different side lengths. which pairs of variables have a linear relationship? check all that apply
Answers: 3
image
Mathematics, 21.06.2019 19:00, joshdunsbuns143
Apool measures 12.3 feet by 16.6 feet. if the longer wall of the pool has a diagonal of 17.8 feet, what is the volume of the pool? (round to nearest tenth)
Answers: 1
image
Mathematics, 21.06.2019 22:10, afrimart1
When is g(x) = 0 for the function g(x) = 5.23x + 4?
Answers: 1
image
Mathematics, 21.06.2019 22:30, SKYBLUE1015
Select all of the following expressions that are equal to 2.5.
Answers: 3
You know the right answer?
a field can be cleared by 33 men in 15days. how many more person required if the field has to be cle...

Questions in other subjects:

Konu
Spanish, 12.02.2021 05:30