A manufacturing company wants to maximize profits on products A, B, and C. The profit margin is $3 for A, $6 for B, and $15 for C. The production requirements and departmental capacities are as follows. Production Requirement by Product
Department
(hours)
Departmental Capacity
(total hours)
A
B
Assembling
2
30,000
Painting
1
38,000
Finishing
2
28,000
What is the maximum profit in this model?
3
ONN
2
1
O A. $57,000
OB. $95.000
C. $225,000
D. $75,000


A manufacturing company wants to maximize profits on products A, B, and C. The profit margin is $3

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 14:40, reginaldboyd28
What is the celsius temperature that is equal to 94 degrees fahrenheit using the formula f=9/5 c+32
Answers: 2
image
Mathematics, 21.06.2019 16:20, jaylanmahone223
Apolynomial function has a root of –6 with multiplicity 1, a root of –2 with multiplicity 3, a root of 0 with multiplicity 2, and a root of 4 with multiplicity 3. if the function has a positive leading coefficient and is of odd degree, which statement about the graph is true?
Answers: 2
image
Mathematics, 21.06.2019 19:30, astigall6360
Asap! i'm not good math and i'm lost.
Answers: 2
image
Mathematics, 21.06.2019 21:00, Jaylen52709
Why is studying fractions important
Answers: 2
You know the right answer?
A manufacturing company wants to maximize profits on products A, B, and C. The profit margin is $3 f...

Questions in other subjects:

Konu
Mathematics, 21.07.2019 22:30
Konu
Mathematics, 21.07.2019 22:30