A construction worker estimates that a kitchen will take 1 Person 200 hours. If 5 people work on the job for 8 hours a day, how many days will it take for them to complete the job? A) 4

B) 5

C) 6

D) 7

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:00, william03300
Aflower has 26 chromosomes. to create a new flower, how many would a sperm cell have what is called?
Answers: 1
image
Mathematics, 21.06.2019 20:00, smariedegray
Aubrey read 29 books and eli read 52 books what number is equal to the number of books aubrey read?
Answers: 1
image
Mathematics, 21.06.2019 23:30, onepunchman20
What is the volume of a rectangular crate that has dimensions 9 inches by 9 inches by 1 feet? 1,458 in.3 121.5 in.3 1,012.5 in.3 36 in.3
Answers: 1
image
Mathematics, 21.06.2019 23:30, zaymuney3063
Which term applies to agb and dge? a. obtuse b. supplementary c. complementary d. vertical
Answers: 1
You know the right answer?
A construction worker estimates that a kitchen will take 1 Person 200 hours. If 5 people work on the...

Questions in other subjects:

Konu
Mathematics, 09.04.2020 22:08