The time required to complete a job varies inversely as the number of people working. It took 22 painters 494 hours to paint a wall. How long
would it have taken 19 people to have done the job?

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:00, eden43
Astore has clearance items that have been marked down by 60%. they are having a sale, advertising an additional 55% off clearance items. what percent of the original price do you end up paying?
Answers: 1
image
Mathematics, 21.06.2019 20:00, ElizabethF
Aball is dropped from a height of 10m above the ground. it bounce to 90% of its previous height on each bounce. what is the approximate height that the ball bounce to the fourth bounce?
Answers: 2
image
Mathematics, 21.06.2019 21:30, michaelgg7166
Can someone explain to me how to do
Answers: 1
image
Mathematics, 22.06.2019 00:40, maxherman
Point b lies between points a and c on . let x represent the length of segment ab in inches. use the segment to complete the statements. the value of x is . the length of in inches is . the length of in inches is .
Answers: 3
You know the right answer?
The time required to complete a job varies inversely as the number of people working. It took 22 pa...

Questions in other subjects:

Konu
Mathematics, 11.11.2020 05:10
Konu
Mathematics, 11.11.2020 05:10
Konu
History, 11.11.2020 05:10
Konu
Mathematics, 11.11.2020 05:10