E LEVEL 5. 35 workers are employed to complete a construction
project in 16 days. Before the project starts, the boss
of the company is told that he needs to complete
the project in 14 days. Assuming that all the workers
work at the same rate, how many more workers does
he need to employ in order to complete the project
on time?

P. S: I need this answer with Proportion (Direct/Inverse) method

ansver
Answers: 1

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 19:30, youcandoit13
Click the arrows to advance or review slides. mapping carbohydrates to food carbohydrates (grams) 15 food (quantity) bread (1 slice) pasta (1/3 cup) apple (1 medium) mashed potatoes (1/2 cup) broccoli (1/2 cup) carrots (1/2 cup) milk (1 cup) yogurt (6 oz.) 12 12 is jennifer's relation a function? yes no f 1 of 2 → jennifer figure out the difference between a function and a relation by answering the questions about her food choices
Answers: 2
image
Mathematics, 21.06.2019 19:30, taylor511176
Celeste wants to have her hair cut and permed and also go to lunch. she knows she will need $50. the perm cost twice as much as her haircut and she needs $5 for lunch. how much does the perm cost?
Answers: 1
image
Mathematics, 21.06.2019 21:00, Mathcat444
The zoo collects $9.60 for every 24 tickets sold. how much will be collected for 400 tickets?
Answers: 2
image
Mathematics, 21.06.2019 22:30, 713073
Which statements about the system are true? check all that apply. y =1/3 x – 4 3y – x = –7 the system has one solution. the system consists of parallel lines. both lines have the same slope. both lines have the same y–intercept. the equations represent the same line. the lines intersect.
Answers: 2
You know the right answer?
E LEVEL 5. 35 workers are employed to complete a construction
project in 16 days. Before the p...

Questions in other subjects:

Konu
History, 01.10.2019 05:30