A can do a piece of work in 10 days and B in 12 days. With the help of C they can finish the work in 4 days. How
long will C take to do it alone?
a) 12 days b) 15 days c) 18 days d) 20 days

ansver
Answers: 2

Other questions on the subject: Mathematics

image
Mathematics, 21.06.2019 18:00, tatibean26
The ratio of wooden bats to metal bats in the baseball coach’s bag is 2 to 1. if there are 20 wooden bats, how many metal bats are in the bag?
Answers: 1
image
Mathematics, 21.06.2019 22:30, BigGirlsTheBest
At the beginning of year 1, carlos invests $600 at an annual compound interest rate of 4%. he makes no deposits to or withdrawals from the account. which explicit formula can be used to find the account's balance at the beginning of year 5? what is, the balance?
Answers: 1
image
Mathematics, 21.06.2019 23:00, edisonsitesuper9312
Joey is asked to name a quadrilateral that is also a rhombus and has 2 pairs of parallel sides. should be his answer
Answers: 1
image
Mathematics, 21.06.2019 23:30, pinkygirlp1662
The triangle shown has a hypotenuse with a length of 13 feet. the measure of angle a is 20 degrees. and the measure of angle b is 70 degrees. which of the following is closest to the length, in feet, of line segment ac? no need to use a calculator to find the trig numbers. each function is listed below. 4.4 5 12.2 35.7
Answers: 2
You know the right answer?
A can do a piece of work in 10 days and B in 12 days. With the help of C they can finish the work i...

Questions in other subjects:

Konu
History, 03.11.2019 07:31